How Long Does a Kitchen Renovation Take in the GTA?

By NextWave Renos · Published November 7, 2026 · 3 min read

Short answer: There is no single number. A kitchen renovation's length depends mostly on how much is changing and on the time spent waiting for cabinets, countertops and permits, not just on construction days. A same-layout refresh moves much faster than a layout change that needs permits, new plumbing and electrical work. The most reliable timeline is a written schedule built from your actual scope and product lead times.

The stages, in order

  1. Design and selections. Layout, cabinets, appliances, countertops, backsplash and lighting. This is where most delays are prevented.
  2. Ordering. Cabinets and appliances are ordered once the design is final. Lead times vary by supplier and product; ask for them in writing.
  3. Permits, if needed. Moving or removing walls and altering plumbing need a Brampton building permit; electrical work needs an Electrical Safety Authority notification.
  4. Demolition.
  5. Rough-ins. Plumbing, electrical and ventilation changes, then any required inspections.
  6. Walls and floors. Drywall, patching and flooring.
  7. Cabinet installation.
  8. Countertop templating, fabrication and installation. Stone countertops are measured after the base cabinets are installed, so there is a gap while they are made.
  9. Backsplash, fixtures, appliances and final touches.

What adds time

Factor Why it matters
Layout changes New plumbing, venting and circuits; often a permit
Custom cabinets Longer manufacturing time than stock
Stone countertops Templating can only happen after cabinets are in
Permit review Ontario's Building Code gives municipalities 10 days to decide on a complete permit application for a house; incomplete applications take longer
Inspections Work must pause until rough-in inspections pass
Changes mid-project Re-ordering and rework
Hidden conditions Old wiring, water damage or uneven floors found during demolition

How to keep your kitchen on schedule

  • Finalize every selection, down to the hardware, before demolition.
  • Confirm cabinet and appliance delivery dates before setting a start date.
  • Ask who applies for permits and books inspections.
  • Plan a temporary kitchen for the weeks without one.
  • Get start and completion dates in your contract. Ontario's guide for renovation businesses says contracts should include a work schedule with start and completion dates.

Our kitchen planning guide covers layout and budget decisions, and our kitchen renovation page explains how we approach each stage.

Want a realistic timeline for your kitchen? We measure the space, review your plans and give you a written estimate with a clearly defined scope.

REQUEST A FREE ESTIMATE

Sources: Ontario Building Code, Division C, 1.3.1.3: permit review periods (PDF) · City of Brampton: Home Improvement brochure (PDF) · Ontario: Guide for home renovation businesses